In civil engineering, what counts is what the ground holds.

The quantities are in the bill of quantities, rock and groundwater in the geotechnical report, and the waste classification in the waste management plan. Scait processes all three and answers your questions on ground conditions and disposal. So you set the unit rate knowing the ground and the classification.

If you also bid in building construction, see the page for building construction.

Excavator in the excavation pit
BordoliFrutigerSchweizerischer Baumeisterverband

Bordoli, a civil engineering and road construction contractor, works with Scait.

More on the Swiss Contractors’ Association

What a cubic metre costs is not stated in the item.

  • The geotechnical report says how much rock and groundwater to expect.

  • The waste management plan sets out how excavated and demolition material is disposed of.

Bill of quantitiesFile in Swiss standard format
Geotechnical reportPDF · 62 pages
Waste management planPDF · 9 pages
Scait
QuantitiesExcavation 4,850 m³Bill of quantities
GroundwaterAround 2.4 m below ground levelGeotechnical report
ClassificationExcavated material slightly contaminatedWaste management plan

Scait reads the bill of quantities and the documents that go with it.

  1. Earthworks balance Scait sets excavation, transport and landfill against each other, working from a bill of quantities supplied as a data file in the Swiss standard format.
Village main road renewal
  1. Question list for civil engineering The list asks about ground conditions and groundwater, the classification of excavated and demolition material, and landfill types and haul routes.
Village main road renewal

Does this also apply to tunnelling and ground engineering?

Underground, in-situ concrete, sprayed concrete, rock support and reinforcement are where the money lies. Your estimators assess these quantities. Scait also reads the contract and conditions for tunnelling and ground engineering.

Let’s talk about your next excavation.

In a meeting we show you what this looks like on a civil engineering tender, from the ground to the landfill.

Book a meeting

Frequently asked questions

Most of our contracts are for public clients. The security required, the deductions and the contractual penalties are fixed. What is the point of knowing them beforehand?

They belong in your price and in your programme, even if you cannot change them. The question list for civil engineering asks about security and deductions.

We are paid on a remeasurement basis. Do we need the quantities reconciled at all then?

In part. With remeasurement, reconciling the quantities matters less. But the unit rate depends on the ground and the classification, and both are in the report and the waste management plan.